PERMANENT AWARD EVIDENCE

School Infrastructure Improvements

Herefordshire Council · published 8 Oct 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release IDe9b297f4-fd3e-46db-8ad8-c11a72a7c753-917066
Open Contracting ID (OCID)ocds-b5fd17-3edc78bc-4ba1-4444-b14c-ef23a7bc8a41
Buyer identifierGB-CFS-53006
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£219,490
award field
Tender value
£400,000
tender field
Procurement method
Other -
Category
works
CPV
45000000
Construction work
Delivery
West Midlands, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

Contract for infrastructure Improvements at 2 x Herefordshire school sites, with an option for additional remedial works. This contract was awarded following a further competition via the Council's Highways and Public Realm Scheme framework. The total value stated in this notice includes the optional works. Please note, the contract commencement date was 27 July 2026, and the contract was formally executed on 25th August 2026. Some dates recorded in the structured notice fields have been adjusted to accommodate system restrictions. The dates set out in this section represent the correct chronology.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

Source-date conflictAt least one reported end date precedes its corresponding start date. Check the official notice before using the schedule.
  1. 01Notice publishedPublication timestamp on the held release8 Oct 2026
  2. 02Tender period startsTender-period field as published26 Jul 2026
  3. 03Tender period endsTender-period field as published26 Jun 2026End precedes start · verify
  4. 04Contract startsContract-period field as published27 Jul 2026
  5. 05Contract endsContract-period field as published12 Oct 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Velta Construction Limited

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 8 Oct 2026 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗