PERMANENT AWARD EVIDENCE

HMPPS Leyhill-Heating Loop Replacement A&B Wing-BPRN No.565/22/9463

Ministry of Justice · published 24 Jun 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release IDd216fdbb-2a2e-4cf5-afa1-83c429378b01-851233
Open Contracting ID (OCID)ocds-b5fd17-f6beff2a-6b59-4b08-9db4-57e06c239c44
Buyer identifierGB-CFS-183111
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£995,637
award field
Tender value
£995,637
tender field
Procurement method
Call-off from a framework agreement
Category
works
CPV
45216113
Prison building construction work
Delivery
Not stated
GL12 8BT
PUBLISHED DESCRIPTION

What the notice says

HMP Leyhill has an old copper pipework infrastructure from the plant rooms to the wing and steel heating loops. All pipework feeding the heating's loops are below ground in a vaulted floor with very limited access. This comes up above the floor to the steel heating loop supplying heating to the cells on all spurs to A & B wings. (385 spaces). The pipework is over 40 years old & has worn so thin that it is regularly being perforated & leaking. Contractors are struggling to access the fractures & are having to cut access hatches into the concrete floor, where they can access the pipework. The pipework is often too thin to affect a repair & must be cut back several times before they are able to make a connection. The repair increases pressure & often cause a further leak a meter along the pipe within a very short period of time. There have been several leaks recently and as the Living block has no spare electrical capacity for emergency heaters & installing a generator close by would be noisy. Potentially we could be looking at a decant of a complete wing if the infrastructure is not addressed prior to a complete failure. A constructor has been appointed for the design and build of the project. This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract. The original estimated value of the contract was calculated by MOJ, and its Cost Consultants following desktop and non-intrusive surveys and was based on information reasonably known at the time and arrived at via a thorough and appropriate methodology. The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £172,758.43.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release24 Jun 2025
  2. 02Tender period endsTender-period field as published11 Jun 2024
  3. 03Contract startsContract-period field as published12 May 2025
  4. 04Contract endsContract-period field as published31 May 2027
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Kier Construction Ltd

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 24 Jun 2025 · held through the daily award projection · Open Government Licence v3.0.