PERMANENT AWARD EVIDENCE

Supply Chain Notice: WC1383775- AK - CIDP - CIDP24- AETHER PHASE 3 URD-Inner citadel security for Airfield Ops, PSD, Cape Gata & EESA (WORKS-Phase3A) - CYPRUS

Ministry of Defence · published 2 Jul 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release IDb1ddbf0b-b232-4bad-a45c-e50fbb16c87b-852425
Open Contracting ID (OCID)ocds-b5fd17-6ead4454-fc69-425c-8788-5cf731750ff2
Buyer identifierGB-CFS-320591
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£717,000
tender field
Procurement method
Other - Other
Category
works
CPV
34928220
Fencing components
Delivery
West Midlands, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

The project requires for the provision of security fence lines and the associated M&E works as per the design and specification carried out under WC2033881. AETHER PHASE 3 includes for security fence replacements, new gates, new concrete bases for CCTV and lighting pole installations, new concrete pits, new power cables & new fence earthing systems (a more detailed scope of works to be provided following positive expression of interest). The Project includes for 4No. different facilities within RAF Akrotiri, Cyprus (Station Armoury, STAR NG, CJCU & CJSU). Maintenance of comprehensive data (type, weight, volume, tipping site) of the rubble waste and other scrap recyclable material collected and removed is a deliverable of this project. Further restrictions/instructions: - Existing topsoil: excavate from required areas to an average depth of 150mm and keep separate, including bulbs. Upon completion of the works topsoil to be spread to areas at the same locations - Trees that need to be trimmed / cut, as per the instructions of Environmental advisor, works should be carried out by Ground Maintenance (CSP JV). - Temporary fence shall be fixed prior the removal of the existing security fence, and to remain during the construction of the new security fence. - Materials to be delivered early on site - Ground maintenance - Environmental restrictions - Antiquities The Provisional Key Tender dates for the project are as follows: - Expression of interest: Wednesday 2nd July 2025 - Expression of interest return: Wednesday 16th July 2025 - Invitation to Tender: Friday 29th August 2025 - Tender Return Date: Monday 29th September 2025 - Contract award (Materials Order): Friday 30th January 2026 - Commencement of work: Monday 16th March 2026 - Completion of work (All Sites): Wednesday 30th September 2026 The currency of this project is Euro (€). The location of this project is Cyprus (British Forces, RAF Akrotiri). Additional information: CONTACT DETAILS: MitieTenderManager@secmitie.co.uk Diamanto.Afxentiou@mod.secmitie.co.uk Konstantinos.Kasiotis@mod.secmitie.co.uk Christos.Ioannides@mod.secmitie.co.uk Phone number: +357 25275267, Mobile: +357 99330211 (Diamanto Afxentiou) Mobile: +357 96900502 (Konstantinos Kasiotis) ATTACHMENTS 1. EOI (Expression of Interest) form 2. PQQ (Pre-Qualification Questionnaire) form Both forms must be completed and returned by the interested tenderers. Work commencement and completion dates will be subject to MOD DIO`s agreement or revisions depending on general site operational requirements or limitations.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release2 Jul 2025
  2. 02Tender period endsTender-period field as published16 Jul 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.