Legionella Related Works

Medicines and Healthcare Products Regulatory Agency · published 13 Jan 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release IDa23f7c58-1976-4096-af1c-326c27c3334d-878936
Open Contracting ID (OCID)ocds-b5fd17-596d03df-b68a-4350-8c3a-6b90c4d6124e
Buyer identifierGB-CFS-329811
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£24,000
award field
Tender value
£24,000
tender field
Procurement method
Call-off from a framework agreement
Category
Not stated
CPV
71333000
Mechanical engineering services
Delivery
Not stated
EN6 3QG
PUBLISHED DESCRIPTION

What the notice says

MHRA general report for legionella works Surveys of each area are not conclusive as some areas are restricted. No access to rooms - 6120, 6023, 6046 - A sum will be allowed by the Client to cover the works for the rooms that were not accessible. Inspection of laboratories were carried out and issues logged where access behind cabinets and benches was available. When works being carried out the contractor and building contractor to be on hand to move cabinets etc. When working in riser cupboards access to affected laboratories will be required to remove any identified issues, make sure all are rectified and outlets can be pulled through to flush, allow contingency sum for unidentified dead legs and toilet and cleaners cupboard areas. Regarding low temperature of hot water service, we would recommend installing a circulating pump on flow with a checked bypass to increase flow. Descaling of outlets, fire stopping and making good etc by building contractor to be provided by the Mechanical contractor. Some services should be taken back to main service pipe in corridors but due to additional works by other contractors they are inaccessible due to cable trays etc. IT Cabling could be an issue to remove. All works listed on survey sheets presume local isolation valves operate and will isolate. Some of the works require complete shutdown of North or South blocks so would need to be out of working hours. Due to the nature and disruption in corridors and laboratories, we would suggest works are carried out weekends. Outlets with minimal usage will need to be surveyed if they are not to be flushed through on a regularly. A good percentage of outlets are not used very often, and a small amount is only drawn off; this does not flush system fully so a program of flushing weekly should be adopted. Allow contingency sum for unidentified issues as they arise when works being carried out. Suggestions for bringing up to specification. Regarding new boosted water dead legs in north block are these to be used in future, if so and to remain then the end should be adapted to allow for regular flushing. As hot water service system main run is oversized a program of replacing with correct sizing would eliminate any hidden dead legs and maintain the correct temperature. All cold-water outlets switched to new boosted cold water service would also eliminate any hidden issues.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release13 Jan 2026
  2. 02Tender period endsTender-period field as published17 Dec 2025
  3. 03Contract startsContract-period field as published12 Jan 2026
  4. 04Contract endsContract-period field as published31 Mar 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Parker Air Conditioning Limited

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 13 Jan 2026 · held through the daily award projection · Open Government Licence v3.0.