PERMANENT AWARD EVIDENCE

HMP Warren Hill Cell Call Replacement - BPRN 800/23/9668

Ministry of Justice · published 21 Feb 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID9e2fc4c4-0742-4408-b858-bd358e60f6b0-829385
Open Contracting ID (OCID)ocds-b5fd17-f53c933b-d581-4b06-8c8f-f4e0c8d69a1a
Buyer identifierGB-CFS-183111
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£2,835,843
award field
Tender value
£2,835,843
tender field
Procurement method
Call-off from a framework agreement
Category
works
CPV
45216113
Prison building construction work
Delivery
East of England, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

The Alder and Oak Unit Cell Call System was reported to be installed in the 1980s and the system is now obsolete due to the lack of spare parts to maintain. The works will consist of a total replacement of the cell call system in the Alder and Oak units and to link all the house units cell call systems back to the main communications room in the gatehouse to provide full monitoring and for communication purposes. The works are to be delivered in line with UK government specification guidelines and Ministry of Justice standards. A constructor has been appointed for the design and build of the project. This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract. It is expected that the total construction cost of the project will be £2,835,843. The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £376,825.05.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release21 Feb 2025
  2. 02Tender period endsTender-period field as published12 Aug 2024
  3. 03Contract startsContract-period field as published11 Feb 2025
  4. 04Contract endsContract-period field as published24 Nov 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Galliford Try Construction Ltd

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 21 Feb 2025 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗