Remediation Works Langbaurgh Mineshaft

The North Yorkshire Council · published 13 Oct 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID9b01f904-0173-46ec-8f64-eb8874dd1be0-917607
Open Contracting ID (OCID)ocds-b5fd17-78f86254-33bd-4ab8-89bf-fbb5bb056e8d
Buyer identifierGB-CFS-245947
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£659,464
award field
Tender value
£659,464
tender field
Procurement method
Restricted procedure
Category
works
CPV
45220000
Engineering works and construction works
Delivery
Yorkshire and the Humber, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

Langbaurgh Closed Landfill Site ('the site') is located on Langbaurgh Ridge, just north of Great Ayton,North Yorkshire. The site is a former Whinstone quarry, which was active from the early 1800s until 1964 and include surface and below ground workings. The site was used as a landfill between 1978 and 1991, infilling the excavation left by surface quarrying to a recorded depth of around 15m. Numerous shafts, adits and below ground voids are understood to underlie the site. The site boundaries are generally very steep, formed by the former quarry walls. One of the shafts near the western end of the site has previously collapsed and been remediated. However, further collapse of the shaft (and remediation) has occurred, forming a roughly circular surface depression above the shaft location. The depression is estimated (from remote surveying) to be 10-15m wide and approximately 6-8m deep. The scheme involves the remedial work for this collapsed mine shaft. The remedial solution adopted comprises the infilling of the existing depression with lightweight aggregates contained by a geotextile 'bag' and covering with a high-strength geogrid reinforced 'soft cap'. The design has been progressed and updated in consultation with various specialist geogrid and lightweight aggregate suppliers in an attempt to deliver a constructible solution. The remedial design is focussed on providing 'betterment' to the site and does not provide a 'designed' solution; nor is the solution to be warranted by WSP or the Contractor against future failures / deviations / collapse.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

Source-date conflictAt least one reported end date precedes its corresponding start date. Check the official notice before using the schedule.
  1. 01Notice publishedPublication timestamp on the held release13 Oct 2026
  2. 02Tender period startsTender-period field as published1 Nov 2026
  3. 03Tender period endsTender-period field as published10 Jul 2026End precedes start · verify
  4. 04Contract startsContract-period field as published1 Nov 2026
  5. 05Contract endsContract-period field as published31 Mar 2028
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Esh Construction Limited

No legal entity is inferred from this supplier name.