PERMANENT AWARD EVIDENCE

Phase 2 Dry Lining, Plastering & Render - Somerford Place - AWARD

GreenSquareAccord · published 21 Feb 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID958c120f-3908-441c-8db0-1819ff01cd59-829341
Open Contracting ID (OCID)ocds-b5fd17-4bb6c529-3d9a-4922-84f1-2d0a9e35da0c
Buyer identifierGB-CFS-298432
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£441,366
award field
Tender value
Not disclosed
tender field
Procurement method
Open procedure
Category
works
CPV
45410000
Plastering work
Delivery
Not stated
B1 2JB
PUBLISHED DESCRIPTION

What the notice says

This GreenSquareAccord tender project is to complete Phase 2 Dry Lining, Plastering & Render at Somerford Place. Contract to be completed by 31st August 2025, followed by a 12 month defect period from the end of the project completion. This tender is being conducted through GreenSquareAccord`s Supplier Portal and all documentation is only available via this portal - https://in-tendhost.co.uk/greensquare Submissions must be made via this portal. All documents are required to be uploaded to the portal and you will then receive a receipt. Should you have any questions about this contract opportunity, please use the messaging facility on the tender project which will direct your question to the GreenSquareAccord colleague leading this procurement. If you experience technical difficulties accessing or using the Portal; user help is available at the help tab on the portal or alternatively, you may contact the In-Tend Support Desk on 0845 5578079 or by email at support@in-tend.co.uk.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release21 Feb 2025
  2. 02Tender period endsTender-period field as published4 Dec 2024
  3. 03Contract startsContract-period field as published30 Mar 2025
  4. 04Contract endsContract-period field as published31 Aug 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

S Thacker Plastering Contractors Limited

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 21 Feb 2025 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗