STANTA-Bodney Camp-Electrical Intake Upgrades to support DNO upgrades

Ministry of Defence · published 13 Feb 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID8aba3642-e2f4-4050-bacc-f64f8b54c11b-883603
Open Contracting ID (OCID)ocds-b5fd17-95a2bc0a-afa9-4f90-9633-76e2f59d43a7
Buyer identifierGB-CFS-292426
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£370,000
tender field
Procurement method
Restricted procedure (above threshold)
Category
works
CPV
45310000
Electrical installation work
Delivery
Not stated
IP26 5BX
PUBLISHED DESCRIPTION

What the notice says

The works required to facilitate uplift of the MIC comprise the following: 1. Construct a plinth for UKPN substation, to their specifications. 2. Install earthing for UKPN substation, to their specifications. 3. Undertake vacuum excavation / trenching (incl back-filling), to their specification, to allow UKPN to: a. Install HV cables between the site boundary and UKPN's new substation. b. 90 mtrs of earth electrode / earth pins in the location shown on UKPN drg 8500348040. 4. Design and construct a new site intake switchroom to include a new LV intake switchboard and requisite earthing. 5. Design and install inter-connecting LV cables as follows: a. Between UKPN new substation and the new site intake switchroom. b. Between the new site intake switchroom and the existing (former) site intake switchroom (to provide a back-feed to the camp). 6. Provide builderswork in connection with items 4 and 5 above, comprising: a. A new plinth for the new LV intake switchboard. b. A new GRP substation enclosure. c. New lighting, small power and background heating for the substation. d. Vacuum excavation / trenching (incl back-filling) for the new LV cables. 7. Provide builderswork to include but not limited to: a. A new plinth for a new GRP enclosure to house meter adjacent to the new substation. b. A new GRP Meter enclosure. c. New lighting, small power for meter GRP as required. d. Ducting to new Substation as required. 8. New handover information and documentation. 9. Provide temporary power for the Camp during the shutdowns.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release13 Feb 2026
  2. 02Tender period endsTender-period field as published6 Mar 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.