PERMANENT AWARD EVIDENCE

EKFB JV - Ancillary Culverts Works package NC2A

Eiffage Kier JV HS2 Main Civils Works, Lots C2 & C3 · published 18 May 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID72b7af58-7914-42be-acc9-4969180ee737-897834
Open Contracting ID (OCID)ocds-b5fd17-f2190199-fc48-41ae-b5bc-1cbdddffefaa
Buyer identifierGB-CFS-179525
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£1,000,000
tender field
Procurement method
Not stated
Category
works
CPV
45221220
Culverts
Delivery
South East, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

NC2A is the North Chilterns to Aylesbury section of C23, a part of the HS2 project managed by the EKFB Joint Venture. We are seeking a specialist subcontractor to undertake the following works within the NC2A section: The Subcontract Works include the provision of all management, labour, materials, plant and equipment, supervision, and other resources necessary and ancillary to safely complete the construction and handover of Ancillary Culverts, as described in the specifications, drawings, HS2 standards Requirements and local authority specifications. - The subcontractor will be responsible for all permanent and temporary work relating to the construction of ancillary culverts and associated works unless otherwise stated in the Works Information including: - Temporary access road and platform construction - Temporary watercourse diversion including over pumping and tie into watercourse. - Temporary excavation for culvert units and headwalls. - Permanent Excavate and replace and removal of soft spot. - Blinding concrete for culvert units, headwalls and retaining walls - Installation of culvert units, including waterproofing at joints and joints details. - FRC works with Headwalls and retaining walls, including waterproofing and joints details. - Temporary edge protection - Supply and Installation of handrails - Completing structural fill surrounding culvert units, headwalls and retaining walls - Installation of riverbed materials and riprap materials - Completing the tie in of watercourse to culvert including reinstatement of temporary diversion. - Testing Please express your interest within this package.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release18 May 2026
  2. 02Tender period endsTender-period field as published22 May 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.

SOURCE

Contracts Finder release

Published 18 May 2026 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗