PERMANENT AWARD EVIDENCE

HMP Bedford Fire Safety Improvements (RETENDER) - BPRN 508/16/1123

Ministry of Justice · published 10 Feb 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID65da7402-ff03-4716-8d1e-5e6b6bff2595-824961
Open Contracting ID (OCID)ocds-b5fd17-29968313-858e-4162-b089-3c483c94ca94
Buyer identifierGB-CFS-183111
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£1,383,894
award field
Tender value
£1,383,894
tender field
Procurement method
Call-off from a framework agreement
Category
works
CPV
45216113
Prison building construction work
Delivery
East of England, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

'- Total replacement of the current Fire Safety systems within the built environment (ie site wide) , utilising hard wired system. - Furthermore, the integration of a number of sustainability initiatives including; replacement of LED lighting, introduction of lighting controls and water saving initiatives. A constructor has been appointed for the design and build of the project. This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract. The original estimated value of the contract was calculated by MOJ, and its Cost Consultants following desktop and non-intrusive surveys and was based on information reasonably known at the time and arrived at via a thorough and appropriate methodology. The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £1,383,894. It is expected that the total construction cost of the project will be c£14m.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release10 Feb 2025
  2. 02Tender period endsTender-period field as published12 Sept 2024
  3. 03Contract startsContract-period field as published3 Feb 2025
  4. 04Contract endsContract-period field as published12 May 2027
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Kier Construction Ltd

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 10 Feb 2025 · held through the daily award projection · Open Government Licence v3.0.