Roof and insulation works at Morgan Centre

Crowthorne Parish Council · published 15 Jan 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID5faa8ef5-7af3-4862-a33d-e43c8bebc66d-817441
Open Contracting ID (OCID)ocds-b5fd17-cd210457-ff60-4c6d-8855-8cecb28539b1
Buyer identifierGB-SRS-supplierregistration.cabinetoffice.gov.uk/77EpxvMC
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£71,625
award field
Tender value
£50,000
tender field
Procurement method
Open procedure (above threshold)
Category
works
CPV
44100000
Construction materials and associated items
Delivery
Not stated
RG45 7LD
PUBLISHED DESCRIPTION

What the notice says

CPC would like to remove the existing failing felt and flashings at the Morgan Centre Community Hall in Crowthorne, Berkshire , check internal gutter seals and current run-off provision, install roof insulation, prepare roof structure to hold PV panels for years to come and then install a new roofing layer. Another tender is currently available for the installation of a solar PV system. These tenders are linked, with the expectation that contractors will liaise with each other with regards to timings so the scaffolding can be used for both projects and that load calculations are complete. Companies are welcome to bid for both tenders if able to deliver both new roof and solar PV system. Additional information: Visits to The Morgan Centre are welcomed - please email projects@crowthorne-pc.gov.uk or call 01344 771 251 to arrange. Questions about the the tender specification should be submitted in writing to projects@crowthorne-pc.gov.uk and questions and answers will then be uploaded to the portal in order that all people viewing the opportunity have access to the same information.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release15 Jan 2025
  2. 02Tender period endsTender-period field as published9 Dec 2024
  3. 03Contract startsContract-period field as published21 Jan 2025
  4. 04Contract endsContract-period field as published21 Mar 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

SOURCE

Contracts Finder release

Published 15 Jan 2025 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗