S30037 Supervision of Construction of Energy Storage Systems Contract (Phase 3c)

National Highways · published 23 Oct 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID5e61f73e-f2cc-4a1e-956c-bf526110be83-869334
Open Contracting ID (OCID)ocds-b5fd17-8a9530cd-10eb-4d67-8d27-48eb08539519
Buyer identifierGB-CFS-322914
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£49,766
award field
Tender value
£49,766
tender field
Procurement method
Call-off from a framework agreement
Category
services
CPV
73220000
Development consultancy services
Delivery
British Oversea Territories
No postcode
PUBLISHED DESCRIPTION

What the notice says

National Highways has tendered via the Crown Commercial Services HELGA dynamic purchasing system for a contract to invest up to £16.6M of Air Quality Designated Funding in delivery of energy storage systems (ESS) at nine motorway service areas (MSAs) to be delivered by Ameresco reference 2022/S 000-007832 referred to hereafter as the Main Contract. The Main Contract contributes to the Government's commitment of providing a minimum of six high-powered electric vehicle charge points per English Motorway Service Area (MSA). The Main Contract will enable the installation of ultra-rapid electric vehicle (EV) charging at locations where electricity grid capacity is insufficient to support delivering the commitment within the required timescales. This is high priority activity for Government set out as an ambition in the Project Rapid Policy Paper and subsequently committed as a 'key stat' in the Department for Transport's Decarbonising Transport - A Better, Greener Britain . The Services provide by the Consultant are for continued support to the Client through the Delivery Phase of the project. The Client awarded the Main Contract to the successful tenderer, referred to hereafter as the Contractor, in December 2022, with delivery of ESS now expected to be completed in mid-2025 to allow high power electric vehicle charging points (HPEVCP) to be commissioned. This contract is for the Consultant to continue to support the Delivery Phase, and follows on from earlier activities (Tasks T0187, T0322, T0419, T0576 and T0663) and will cover: - the continuing provision of elements of the Engineering and Construction Supervisor service for the Client, as defined in this scope and, referred to hereafter as the Supervisor - Providing continued ad-hoc technical, commercial, or other support for the Main Contract as required by the Service Manager.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release23 Oct 2025
  2. 02Tender period endsTender-period field as published15 Oct 2025
  3. 03Contract startsContract-period field as published22 Oct 2025
  4. 04Contract endsContract-period field as published31 Mar 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Costain Limited

No legal entity is inferred from this supplier name.