PERMANENT AWARD EVIDENCE

Supply Chain Notice: Portsmouth Naval Base Gas Works

Ministry of Defence · published 26 Feb 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID540c9bc7-277b-4766-a59f-8b3c7da18eb7-830515
Open Contracting ID (OCID)ocds-b5fd17-ae7a6d9f-fab9-4f40-a620-2fbd2d0e675c
Buyer identifierGB-CFS-310978
Release typeplanning
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£1,500,000
tender field
Procurement method
Not stated
Category
Not stated
CPV
09121200
Mains gas
Delivery
Not stated
PO1 3LS
PUBLISHED DESCRIPTION

What the notice says

A full review of all gas safety shut off systems within living accommodation and catering blocks to ensure compliancy and to reduce breakdown tasks where the gas system needs manually resetting, then replacing, as necessary. systems (Solenoid valves, extraction systems, gas detection units, forced ventilation interlocks, ect.) and a full review and replacement of obsolete/broken equipment, and replaced with up to date, compliant safety equipment. The short-to-medium term strategy for the NPC for Level 3 Sub-elements shall be based on a hierarchy of solutions that best reflects the future of the particular buildings concerned, for example. 1. Electric Heat Pumps (high temperature, CO2, heat pumps, cascade etc.) 2. Hybrid Heat Pumps (gas fired and air source) 3. Conventional gas fired boilers The solution for a particular building should be based on the following criteria. 1. Opportunity for a district heat network linked to other buildings 2. Pay-back period (given the potentially short asset lifecycle) 3. Thermal performance of the building and requirement for building fabric improvements e.g. double glazing and insulation 4. The requirement for pipework and emitter upgrades 5. Available footprint for internal/external plant 6. Spare capacity in electrical distribution boards, where applicable 7. Lead-time of equipment and installation/commissioning period 8. All works to be kept in alignment with Net Carbon Zero (NCZ) Strategy

Tender statusplanned
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release26 Feb 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.

SOURCE

Contracts Finder release

Published 26 Feb 2025 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗