PERMANENT AWARD EVIDENCE

Lancaster Street Retaining Wall Rebuild

Cumberland Council · published 26 Feb 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID4bee7c64-e120-4024-859b-a8397ac4676c-830665
Open Contracting ID (OCID)ocds-b5fd17-5731afb4-0a5b-4854-b700-ad9f47ee9e06
Buyer identifierGB-CFS-242784
Release typeaward
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
£63,516
award field
Tender value
£63,516
tender field
Procurement method
Other -
Category
works
CPV
45233000
Construction, foundation and surface works for highways, roads
Delivery
England, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

The Council is procuring a contract to undertake the reconstruction of a section of retaining wall at Lancaster Street, Carlisle. O.S. grid Co-ordinates 340443E; 555372N. The works require a section of retaining wall approximately 27m in length and 1.5m in height of retaining wall to be taken down and reconstructed/ realigned as indicated on drawing Dwg-01-Lancaster Street RW. The existing stone is to be set aside for re-use and where replacement stone is required it must match the surrounding masonry as closely as possible. The existing parapet railings are to be refurbished and reinstalled. The perforated drainage pipe behind the retaining wall is to be connected to the existing gully. The cobbled surface on Lancaster Street is to be reinstated to existing levels. Cumberland Council have arranged a GPR survey to be undertaken to accurately locate services and the report will be shared with the contractor. A road closure permit for Lancaster Street and Crown Street to complete the works has been obtained by Cumberland Council. The closure commences on Monday 10th March 2025 for a duration of up to 6 weeks concluding Thursday 17th April 2025. A key objective is to limit disruption to local residents, businesses and members of the public during the works, any road closures should be kept to a minimum. The Contractor shall also be responsible for procuring and managing all traffic management, which is to be agreed upon with the Employer's Highway Network Manager.

Tender statuscomplete
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release26 Feb 2025
  2. 02Tender period endsTender-period field as published21 Feb 2025
  3. 03Contract startsContract-period field as published24 Feb 2025
  4. 04Contract endsContract-period field as published2 May 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

Published name only

Metcalfe Plant Hire

No legal entity is inferred from this supplier name.

SOURCE

Contracts Finder release

Published 26 Feb 2025 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗