PERMANENT AWARD EVIDENCE

P15 Dampers and Actuators - Costain HRS02 Tunnel and Lineside M&E

Costain Group PLC · published 15 Oct 2025. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID2ed4ba9d-5e60-46a2-a67f-4319f5daf36c-868278
Open Contracting ID (OCID)ocds-b5fd17-b2c84a6f-436d-4d3f-8012-d5d76d9048ac
Buyer identifierGB-CFS-325210
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£5,000,000
tender field
Procurement method
Not stated
Category
goods
CPV
31131100
Actuators
Delivery
West Midlands, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

Costain have been appointed to deliver contract HRS02, the Tunnel and Lineside Mechanical and Electrical services for HS2 ltd. A high-speed railway project that connects London to Birmingham with plans to extend in the future. Package 15 Dampers and Actuators scope for contract HRS02 consists of dampers and actuators within the headhouses and ventilation shaft areas of the railway, the route being circa 180 km in length, inclusive of; - Fan Isolation Dampers - Tunnel Isolation Dampers - Associated Actuators and Limit Switches - Associated Panels Costain require a supplier for design and supply only of the damper and actuator package. Costain and HS2 are looking for innovative and smart solutions that provide benefits in the following key areas; - Health and Safety - Programme - Installation and commissioning efficiency - Cost - Quality and Assurance efficiency - Whole life cost - Carbon efficiency All the innovation and design development must be accompanied with a rigorous approach to ensuring that the technical requirements are met. Including testing, where necessary. The scope of the design and supply will include the following; - Support to Costain's design partner through concept and detailed design - Ventilation analysis, modelling and calculations - Testing of products and arrangements - Provision of samples and mock ups - Commissioning support, as required Full details of the scope and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of the HS2 project and are to assess their internal capabilities to be able to carry out the intended scope of works prior to completing the expression of interest.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release15 Oct 2025
  2. 02Tender period endsTender-period field as published30 Oct 2025
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.