PERMANENT AWARD EVIDENCE

WP1140 - T5D Design Consultant

Costain Limited (H7-Heathrow) · published 2 Jun 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID2a1ded63-c1d7-4984-9540-4dd819838020-900110
Open Contracting ID (OCID)ocds-b5fd17-abb75190-6054-4f95-b2a7-26ec9ecfbe8d
Buyer identifierGB-CFS-271218
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£5,000,000
tender field
Procurement method
Not stated
Category
services
CPV
71320000
Engineering design services
Delivery
London, United Kingdom
No postcode
PUBLISHED DESCRIPTION

What the notice says

The T5D Rail-tunnel Ventilation Shaft is located adjacent to T5D at its North and can be accessed from the bottom (Level 6) via the trackside of the HEX tunnel or from the top (level 7) via Airside. The objective is to replace the four attenuators in the T5D Shaft because they are at their end of life. The renewal of the T5D attenuators aims to reduce the risk of debris entering fans, tunnels and station, prevent the fans from failing in any fire scenario and provide ventilation and smoke clearance for the Heathrow Rail Tunnels. This improves safety conditions within Heathrow Rail Tunnels and improves resilience of systems. In addition, less maintenance and repair are required for the attenuator. Each attenuator is formed of four quadrants weighing around 1160 kg. Review MEP systems along the airflow and advise replacement/modification to bring them up to compliance. Surveys will be carried out by others (Employed by the Client) under the direction of the Design Consultant Item Question Q1 Do you have experience with Underground rail network ventilation resilience? Requirement: Ventilation Resilience Report required for the HAL Rail underground network. Q2 What capability do you have of air flow modeling for fans / attenuators etc.? Requirement: Model the existing configuration with one fan operating, and both fans operating and then repeat the modelling with shaft sub divided to allow one set of attenuators to be replaced while the other is operational. Q3 What capability do you have of understanding the requirements for specifying replacement attenuators etc., Specifically considering the constraints of an operational rail network? Note: - RIBA 5 onwards including construction is excluded.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release2 Jun 2026
  2. 02Tender period endsTender-period field as published9 Jun 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.

SOURCE

Contracts Finder release

Published 2 Jun 2026 · held through the daily award projection · Open Government Licence v3.0.

Inspect the official JSON release ↗