A66 - FRC

BALFOUR BEATTY CIVIL ENGINEERING LIMITED · published 20 Feb 2026. This page preserves the identifiers and current held fields for one Contracts Finder release; it is not an invoice, performance assessment or complete contract history.

Contracts Finder release ID15b9dd11-eb63-4e2b-938a-111669d769b5-885020
Open Contracting ID (OCID)ocds-b5fd17-93cf6f64-e302-4b8e-9b23-f123eeee00f6
Buyer identifierGB-SRS-supplierregistration.cabinetoffice.gov.uk/UfZq8heB
Release typetender
PUBLISHED COMMERCIAL FIELDS

Values stay separate.

A tender estimate and an award value answer different questions. Neither is treated as cash paid.

Award value
Not disclosed
award field
Tender value
£5,000
tender field
Procurement method
Competitive procedure with negotiation (above threshold)
Category
works
CPV
45262310
Reinforced-concrete work
Delivery
Not stated
CA10 1XQ
PUBLISHED DESCRIPTION

What the notice says

The package covers, but is not limited to, the following structural components: Abutments, including bearing shelves, backwalls, and associated retaining elements Wing walls including reinforcement details, formwork, concrete placement, and tie-ins Central pier, where applicable, based on design Placing of pre-cast deck panels, including the stitched slab, diaphragms, upstands and any longitudinal or transverse construction joints Installation precast parapet plinths and associated edge thickening or upstand requirements Any additional minor or connecting works required to complete the structure to specification In addition to the primary structural FRC installation, the package includes full responsibility for all associated temporary works and ancillary requirements, including: Temporary works design, supply and installation, inclusive of falsework, propping, support systems, working platforms and stability measures Testing and control activities, including concrete cube testing, slump testing, rebar inspection hold points, and pour records Curing systems and processes including curing membranes, coverings, and controlled curing regimes Concrete temperate monitoring, including the provision and management of sensors where required Access and edge protection systems including surface preparation, treatment, defect rectification (if required) and final concrete finishes All labour, plant, materials, consumables, and supervision to deliver a fully compliant structure The contractor will be required to coordinate their works with adjacent section 3b activities and provide all necessary RAMS, ITPs, quality records, and as-built-information to support completion of Centre Parcs overbridge.

Tender statusactive
STAGE-DATE LEDGER

Reported dates, without an invented lifecycle.

The current projection contains one award release, not a verified chain of planning, tender, award, contract and modification records. Dates are shown in source-field order and are not silently repaired.

  1. 01Notice publishedPublication timestamp on the held release20 Feb 2026
  2. 02Tender period endsTender-period field as published6 Mar 2026
SUPPLIER EVIDENCE

Published names and exact identifiers

A company profile appears only when this release carries a usable company number. Name-only suppliers remain name-only.

No supplier is named in this projection. That does not prove the notice had no supplier in every source version.